Building Austin's New Central Library Takes 1,000 Concrete Trucks. They're All Coming This Weekend.

Approximately 1,000 concrete trucks are needed to pour a five-foot foundation for Austin's new central library. The 24-hour pour starts tonight at 10 p.m.
Reddit user TheKnitro, http://redd.it/252o03

Here's a reason to avoid the Seaholm area near Cesar Chavez Street tonight: over 1,000 concrete trucks from Austin and surrounding cities constantly rotating through the area for over 24 hours.

The City of Austin is building a new central library at 701 W. Cesar Chavez, near the former Seaholm power plant. Tonight, construction crews are putting in a five-foot deep concrete slab to create the building’s foundation. That’s a big project – requiring a total of 1,020 concrete trucks.

Read more
Libraries
3:55 pm
Mon August 19, 2013

For You To Borrow, Some Libraries Have To Go Begging

The Tyson Library in Ludlow, Vt., is required to support itself independently; public libraries in Vermont receive no state funding.
Neda Ulaby NPR

Originally published on Mon August 19, 2013 3:14 pm

More than 90 percent of Americans say public libraries are important to their communities, according to the Pew Research Center. But the way that love translates into actual financial support varies hugely from state to state.

Vermont, for instance, brags that it has more libraries per capita than any other U.S. state. Some of them are remarkably quaint. In Ludlow, one library is a white clapboard Victorian, slightly frayed, ringed by lilies and sitting by the side of a brook.

Read more
Austin
5:30 pm
Thu February 7, 2013

Seaholm Substation Cleanup Complete

A decontamination crew removed 32,000 tons of soil.
INTERA

Arsenic, lead and the byproducts of burned oil were some of the contaminants found underneath an electrical substation at the Seaholm power plant downtown.

The land will eventually be home to Austin’s new central library. Those contaminants have now been removed and the Texas Commission on Environmental Quality has issued its seal of approval.

Read more
Austin
3:59 pm
Fri July 6, 2012

Looking Back at Austin's 'Library For the Future'

A rendering of the new central library, along Cesar Chavez Street.
City of Austin

A new central library – an updated replacement for the 1970s-era  Faulk Central Library downtown – has been in the works since 2006. It was that year that voters approved $90 million in bonds to finance the project.

Six years later, and construction hasn’t  started on what the city touts as the “library for the future.” And the Austin City Council recently approved an additional $1.3 million in funding.  

In the spring of 2008, the Council approved the library’s site, nestled between the slated-for-redevelopment Seaholm Power Plant, and the site of the former Green Water Treatment Plant.  The library was officially defined as the “Library for the Future” when the council approved an “Architectural Program Building Narrative” later that year. That’s also when the council also selected the architects to guide the project.

Read more